Skip to main content
Skip to download form

Free equipment commissioning checklist

Download a free equipment commissioning checklist. Verify installation, testing, calibration and handover for new equipment. PDF download.

Two ways to use it

Use in MapTrack →

Get this form free

Use it digitally

Unlimited users

These same 25 checks, already built.

G2 rating 4.9 out of 5
Source: G2.com, Inc.
Capterra rating 5.0 out of 5GetApp rating 5.0 out of 5Software Advice rating 5.0 out of 5
All MapTrack reviews
  • Scan the asset’s QR tag with any phone
  • Submitted forms can trigger alerts
  • Photos on fails, audit-ready records
  • Export responses, PDF reports with your logo

Free trial. No credit card needed.

Trusted by teams across Australia and New Zealand

We respect your privacy. Unsubscribe anytime.

These templates are free general guides provided as-is. They do not constitute legal, safety or compliance advice. You are responsible for ensuring any form meets your specific workplace obligations, industry standards and applicable regulations.

Updated 26 Oct 2026

Equipment Commissioning Checklist

New equipment installation and acceptance verification

0 of 25 checks

Delivery Verification

1Equipment matches purchase order specifications
2Serial number and model confirmed against documentation
3No visible shipping or transit damage
4All components, accessories and spares received
5Documentation package complete (manuals, certificates, drawings)

Installation Checks

6Foundation or mounting adequate and level
7Electrical connections correct (phase, voltage, earthing)
8Hydraulic and pneumatic connections secure and leak-free
9Alignment and levelling within tolerances
10All fluids filled to correct levels (oil, coolant, hydraulic)

Safety Systems

11Emergency stop functions tested and operational
12Guards and safety interlocks fitted and tested
13Overload protection devices calibrated and tested
14Warning labels and safety signage installed
15Limit switches and proximity sensors operational

Functional Testing

16No-load operation test completed satisfactorily
17Full-load operation test completed satisfactorily
18All control functions respond correctly
19Performance parameters within specification
20No abnormal noise, vibration or temperature

Documentation

21Asset registered in maintenance management system
22Maintenance schedule established and entered
23Operator training completed and records filed
24Risk assessment completed for new equipment
25Warranty registration completed with supplier

Commissioning Engineer Sign-off

Signature

Print name

Date

Site Manager Acceptance

Signature

Print name

Date

How to use: download the PDF, print or complete digitally on any device.

  • PDF format, ready to print or fill on screen
  • Use as-is or customise to suit your operation
  • Go digital in MapTrack for photos, reminders and audit trails

Don't just download it - use it live. Start a free workspace with this equipment commissioning checklist already built, so your crew can run it from a phone.

Jarrod Milford

Jarrod Milford

Co-Founder & Commercial Director

Updated 26 October 2026

Short answer

An equipment commissioning checklist records the checks that new equipment is installed correctly, safe and performing to specification before it goes into service, ending in a handover sign-off. Project engineers and maintenance teams complete it at installation and after major overhauls or relocations. Regulation 204 of the model WHS Regulations requires competent people to commission plant, only once it is established as without risk so far as reasonably practicable.

Checked against Model WHS Regulations as at 5 December 2025 (cited within as the Work Health and Safety Regulations 2011) on by the MapTrack templates team. How we check templates

Key takeaways

  • The MapTrack equipment commissioning checklist contains 25 checks across 5 sections. Sections covered: Delivery Verification, Installation Checks, Safety Systems, Functional Testing, Documentation.
  • Installation puts the equipment in place. Commissioning proves it performs to specification under load before it is handed to operators.
  • A failed test stops the handover. Commissioning that continues past a failure records an assumption rather than a result.
  • Capture the as-commissioned settings and readings. They are the baseline every later service and fault diagnosis is measured against.
  • Under the model WHS Act the primary duty of care covers plant before it is used, so commissioning records show it was safe at handover.

Enter your email below to download this equipment commissioning checklist as a ready-to-use PDF.

Used by construction, mining and field service teams

Saunders InternationalMineral ResourcesSupagasHacer GroupMetro TunnelUltrabuilt

What is an equipment commissioning checklist?

An equipment commissioning checklist is a structured document used to verify that new or refurbished equipment has been correctly installed, tested, calibrated and is ready for operational service. The checklist covers delivery verification, installation checks, safety system testing, functional testing, calibration, documentation review, operator training, asset registration and formal handover to operations.

Commissioning is the critical phase between equipment installation and operational use. It ensures that the equipment meets the design specifications, operates safely, is registered in the asset management system and that operators are trained to use it correctly. Under Section 19 of the WHS Act 2011, the PCBU has a duty to ensure that plant is safe to use. Commissioning is the process that verifies safety before the equipment enters service. Skipping or rushing the commissioning process risks safety incidents, premature failures, warranty issues and operational disruption.

Learn more about asset tracking in MapTrack.

Commissioning stages

Commissioning usually runs in stages. Pre-commissioning comes first: mechanical completion checks, cleaning and flushing, utility connections and confirming the equipment is installed as designed, before it is run under load.

For major equipment, a factory acceptance test (FAT) at the manufacturer's works checks the equipment against the agreed specification before it ships. A site acceptance test (SAT) then checks it against agreed acceptance criteria once it is installed and connected to site power, controls and process. The contract or commissioning plan sets each test's scope.

Commissioning proper then runs the equipment under load against its design parameters. Where a process will handle hazardous chemicals, plan a pre-startup safety review (PSSR) before they are first introduced, confirming construction matches the design, procedures are in place and operators are trained. Check whether the law for your process and jurisdiction makes one mandatory.

Handover transfers the equipment to operations with the as-commissioned settings, manuals, training records and any open punch-list items. Related checklists cover plant, HVAC systems and registering the item as an asset.

Get the free template

Enter your email above to download the full equipment commissioning checklist as a PDF.

Benefits of using this equipment commissioning checklist

  • Safety assurance: verify that all safety systems, guards, emergency stops and interlocks are functioning before the equipment enters service.
  • Specification compliance: confirm the equipment meets purchase specifications, design parameters and performance requirements.
  • Warranty protection: documenting a proper commissioning process protects warranty claims by demonstrating the equipment was installed and started correctly.
  • Asset registration: the commissioning process ensures the equipment is registered in the asset management system with all relevant details.
  • Operator readiness: verifying that operators have been trained before handover reduces the risk of misuse and damage.
  • Audit trail: a completed commissioning checklist provides documented evidence that due diligence was followed before equipment use.

Benefits of digitising forms in MapTrack

When you move your checklists from paper to MapTrack, you get:

  • Field users can easily scan a QR code to complete a form on mobile. Unlimited users.
  • Email the right people when a form is submitted, with an automation you set up.
  • File every completed form against the asset, location or person it covers.
  • Download any completed form as a PDF, with failed answers listed at the top.
  • Fill in forms offline; they upload when the device is back online.
  • Build conditional logic (show or hide questions based on answers).
  • Take pictures or attach photos. Not possible with a paper-based form.
  • Electronic signatures.
  • Edit forms later without reprinting.
  • Set who can view, fill in or edit forms with user roles.
  • Upload a paper form (PDF, Word, Excel or a photo) and MapTrack's AI builds a digital version for you to check.
  • Keep one asset register with each asset's location, condition and custody history.
  • Schedule calibration and record certification and warranty expiry dates against each asset.
  • See each asset's value over time in the Asset Depreciation report.

Book a demo to see how MapTrack handles checklists.

Try MapTrack free

Full access to every feature. No credit card required. Per-asset pricing so you scale as your fleet grows.

  • No credit card required

1-2 days/week saved

“Bloody amazing! We used to spend 1-2 days a week tracking and managing our generators alone.”
Saunders International

Steve McAllister

Asset Coordinator, Saunders International

What to include in an equipment commissioning checklist

This equipment commissioning checklist covers 10 key areas:

  • Equipment details: description, make/model, serial number, purchase order number, supplier, warranty details.
  • Delivery verification: items received match order, no transport damage, documentation complete (manuals, certificates, SDS).
  • Installation checks: installed per manufacturer instructions, foundations/mounting secure, utilities connected (power, compressed air, water), alignment verified.
  • Safety systems: guards in place, emergency stops functional, interlocks operational, warning labels applied, electrical safety tested.
  • Functional testing: power-on test, dry run, loaded test, performance against specification, accuracy and repeatability.
  • Calibration: instruments calibrated, calibration certificates filed, next calibration date set.
  • Documentation: operating manual available, maintenance manual available, spare parts list, circuit diagrams, as-installed drawings.
  • Asset registration: asset ID assigned, entered in asset register, location recorded, warranty details entered, maintenance schedule established.
  • Operator training: operators identified, training delivered, competency verified, training records filed.
  • Handover: commissioning engineer sign-off, operations acceptance, both parties sign.

How to use this equipment commissioning checklist

  1. Verify the delivery against the purchase order and inspect for transport damage.: Check that all items received match the purchase order, including the equipment, accessories, spare parts and documentation. Inspect for any damage that may have occurred during transport. Document any discrepancies or damage and notify the supplier immediately.
  2. Verify the installation meets manufacturer specifications.: Check that the equipment is installed on the correct foundations or mounting, level and secure. Verify utility connections (power supply, compressed air, water, drainage) are correct and meet the equipment requirements. Confirm alignment with any connected equipment.
  3. Test all safety systems before any operational testing.: Test every emergency stop button, safety interlock, guard switch and warning device. Verify that the equipment stops safely when safety systems are activated. Confirm that all guards are in place and secure. Check that warning labels and safety signage are applied.
  4. Conduct functional testing and calibration.: Run the equipment through a complete functional test cycle: power on, dry run (no load), loaded test, and performance measurement against the specification. Calibrate all instruments and measuring devices. Record test results and calibration certificates.
  5. Complete asset registration, operator training and formal handover.: Register the equipment in the asset management system with all relevant details. Establish the maintenance schedule. Deliver operator training and verify competency. Complete the commissioning checklist, obtain sign-off from the commissioning engineer and the operations team, and formally hand over the equipment for service.

In MapTrack, you can manage your full asset register digitally. Each submission is stored as a timestamped PDF against the asset record.

Get the free templateEnter your email above to download the full equipment commissioning checklist as a PDF.Back to download form

How often should you complete this checklist?

Equipment commissioning is performed once when new equipment is first installed and put into service. It should also be performed after major overhauls, refurbishments or relocations that could affect the equipment installation, safety systems or performance.

Try MapTrack free

Full access to every feature. No credit card required. Per-asset pricing so you scale as your fleet grows.

  • No credit card required

Frequently asked questions

What is the difference between commissioning and installation?

Installation is the physical process of placing, mounting and connecting the equipment. Commissioning is the verification process that follows installation, confirming that the equipment was installed correctly, operates safely, meets performance specifications and is ready for operational use. Installation is about building it. Commissioning is about proving it works.

Who should be involved in equipment commissioning?

Commissioning typically involves the supplier or manufacturer (or their commissioning engineer), the installer, the maintenance team, the safety manager and the operations team who will use the equipment. The supplier verifies the equipment, the maintenance team ensures it is registered and maintainable, and the operations team confirms it meets their requirements and that operators are trained.

What if the equipment fails a commissioning test?

If the equipment fails any commissioning test, it must not be released for operational use until the issue is resolved. Document the failure on the checklist, notify the supplier if the issue is a defect and arrange for repair, adjustment or replacement. Retest the failed item after correction. Only sign off the commissioning when all tests pass.

Is this equipment commissioning checklist free?

Yes. This equipment commissioning checklist is completely free to download and use. Enter your email on this page and it downloads as a ready-to-print PDF. No MapTrack account is required. If you want digital commissioning workflows with photo capture and automated asset registration, MapTrack can help.

How long should commissioning records be retained?

Retain commissioning records for the life of the asset, plus seven years after disposal. AS 4024.1:2014 (Safety of machinery) treats the commissioning record as part of the technical file for the machine, which must be available throughout the equipment service life to support modifications, repairs and re-commissioning. The WHS Regulations 2011 require commissioning and test records only for specific plant, such as registered plant (regulation 237) and plant with presence-sensing safeguarding (regulation 226), and most manufacturer warranties require the original commissioning evidence to be produced when a warranty claim is lodged. For pressure equipment and lifting plant subject to AS/NZS 3788 or AS 2550 in-service inspection regimes, commissioning records become part of the in-service inspection history and must be retained on that basis.

Applicable regulatory standards

This template is a starting point. Check the current requirements that apply to your equipment, work and location. The template alone does not establish compliance.

  • Model Work Health and Safety Regulations

    Edition: Model WHS Regulations as at 5 December 2025 (cited within as the Work Health and Safety Regulations 2011)

    Requires competent commissioning, only once plant is established as without risk so far as is reasonably practicable; this checklist records the checks and results.

    • Part 5.1: General duties for plant and structures for designers, manufacturers, importers, suppliers, installers and those managing or controlling plant.
    • reg 204: Plant must not be commissioned, decommissioned or dismantled unless risks are eliminated so far as reasonably practicable, and the work must be done by a competent person.

    Safe Work Australia (drafted by the Parliamentary Counsel's Committee)

  • Model Work Health and Safety Act (Model Work Health and Safety Bill)

    Edition: Model WHS Bill as at 5 December 2025 (includes the Model WHS Legislation Amendment (Incident Notification) 2025)

    The primary duty of care and the duty of those who install or commission plant, which the handover record evidences.

    • s 19: Primary duty of care: a PCBU must ensure, so far as is reasonably practicable, the health and safety of workers and others, including safe plant, systems, training and supervision.
    • s 26: Duty of PCBUs that install, construct or commission plant or structures.

    Safe Work Australia (drafted by the Parliamentary Counsel's Committee)

  • Safety of machinery (AS 4024 and AS/NZS 4024 series)

    Edition: Multi-part series; each part has its own edition (for example AS 4024.1100:2019, AS/NZS 4024.1601:2024, AS/NZS 4024.1603:2019)

    Machinery safety series covering guards, interlocks and emergency stops; cite the current part for the machine being commissioned.

    Standards Australia and Standards New ZealandSold by the publisher

  • 29 CFR Part 1910, Occupational Safety and Health Standards

    Edition: Current eCFR text, up to date as of 2026-10-22 (read 2026-10-26)

    US process safety management: a pre-startup safety review before highly hazardous chemicals enter new or significantly modified covered processes.

    • 1910.119(i): Requires a pre-startup safety review of new and significantly modified covered processes before highly hazardous chemicals are introduced.

    US Occupational Safety and Health Administration (text via eCFR)

Each source was read at its publisher and the page checked on 26 October 2026. The publisher's current text is the authority.

Equipment commissioning checklist preview

Equipment commissioning checklist template preview showing fields and layout

The numbers behind this equipment commissioning checklist

The pages below gather the figures behind this kind of check. Each figure on them carries its source and date, so you can quote it in a toolbox talk, a budget case or a board paper without chasing the original report.

Get the free template

Enter your email above to download the full equipment commissioning checklist as a PDF.

Embed this free template on your website

Run an industry blog, trade association site, or training resource? Drop a preview of this free equipment commissioning checklist straight into your page. The snippet is self-contained, needs no scripts, and links readers back to the full free template.

<div style="max-width:480px;font-family:system-ui,-apple-system,'Segoe UI',Roboto,sans-serif;border:1px solid #E5E7EB;border-radius:12px;padding:20px;background:#ffffff;">
  <p style="font-size:12px;font-weight:700;letter-spacing:0.05em;text-transform:uppercase;color:#071D49;margin:0;">Free template</p>
  <p style="font-size:18px;font-weight:700;color:#071D49;margin:6px 0 0;">Equipment commissioning checklist</p>
  <ul style="margin:12px 0 0;padding-left:18px;color:#374151;font-size:14px;line-height:1.6;">
    <li style="margin:4px 0;">Equipment details: description, make/model, serial number, purchase order number, supplier, warranty details.</li>
    <li style="margin:4px 0;">Delivery verification: items received match order, no transport damage, documentation complete (manuals, certificates, SDS).</li>
    <li style="margin:4px 0;">Installation checks: installed per manufacturer instructions, foundations/mounting secure, utilities connected (power, compressed air, water), alignment verified.</li>
    <li style="margin:4px 0;">Safety systems: guards in place, emergency stops functional, interlocks operational, warning labels applied, electrical safety tested.</li>
    <li style="margin:4px 0;">Functional testing: power-on test, dry run, loaded test, performance against specification, accuracy and repeatability.</li>
    <li style="margin:4px 0;">Calibration: instruments calibrated, calibration certificates filed, next calibration date set.</li>
  </ul>
  <p style="font-size:13px;color:#6B7280;margin:14px 0 0;padding-top:12px;border-top:1px solid #E5E7EB;">Free <a href="https://www.maptrack.com/templates/equipment-commissioning-checklist" style="color:#071D49;font-weight:600;text-decoration:none;">Equipment commissioning checklist</a> by MapTrack</p>
</div>

Free to reuse, including commercially. This template is published under a Creative Commons Attribution 4.0 licence. Copy it, adapt it, put it on your own site or in your own docs. All we ask is that you credit MapTrack with a link back to this page. The snippet above already includes that credit, so if you use it as-is you’re covered.

Cite this template

Writing about this topic? You’re welcome to quote this checklist. Here’s the wording to use so your readers can find the original.

The MapTrack equipment commissioning checklist contains 25 checks across 5 sections.

Short attribution
MapTrack Equipment commissioning checklist, https://www.maptrack.com/templates/equipment-commissioning-checklist
Reference list
MapTrack. (2026). Equipment commissioning checklist [Checklist template]. Retrieved from https://www.maptrack.com/templates/equipment-commissioning-checklist

Free to reuse with credit under a Creative Commons Attribution 4.0 licence. If you’d rather link straight to it, the page is https://www.maptrack.com/templates/equipment-commissioning-checklist.

Need to manage your full asset register digitally?

Register every asset in MapTrack, attach digital forms, and get a complete history of every inspection, service and compliance record.

Asset tracking · All templates · Pricing · Book a demo