Skip to main content
Skip to download form

Free plant commissioning checklist

Jump to download form ↓

Enter your email below to download this plant commissioning checklist as a ready-to-use PDF.

Free plant commissioning checklist (PDF-ready). Verify delivery, install, pre-commissioning, function and safety tests, and handover to operations.

Jarrod Milford

Jarrod Milford

Commercial Director

Updated 22 June 2026

Key takeaways

  • A plant commissioning checklist verifies install, pre-commissioning, function and safety tests, documentation and handover.
  • It is broader than generic equipment commissioning because plant is installed and needs staged install and pre-commissioning checks.
  • Pre-commissioning confirms it is safe to energise; commissioning then proves it works and is safe to operate.
  • Commissioning data, manuals and settings captured at handover become the baseline for the machine history.
  • A signed commissioning record is evidence that WHS commissioning duties and AS 4024 safe-operation checks were met.

Updated 22 June 2026

How to use: download the PDF, print or complete digitally on any device.

  • PDF format, ready to print or fill on screen
  • Use as-is or customise to suit your operation
  • Go digital in MapTrack for photos, alerts and audit trails

Download free PDF template

FreePDFUpdated June 2026

Get your free template

Enter your email to download the plant commissioning checklist as a free PDF. No sign-up required to use it.

Rated 4.9 on G2Rated 4.9 on Capterra
Your info is secure. No spam, ever.

These templates are free general guides provided as-is. They do not constitute legal, safety or compliance advice. You are responsible for ensuring any form meets your specific workplace obligations, industry standards and applicable regulations.

G2 rating 4.9 out of 5Capterra rating 4.9 out of 5

Trusted by teams across Australia and New Zealand

We respect your privacy. Unsubscribe anytime.

Used by construction, mining and field service teams

Saunders InternationalMineral ResourcesSupagasHacer GroupMetro TunnelUltrabuilt

What is a plant commissioning checklist?

A plant commissioning checklist is the staged verification that brings new fixed or mobile plant into service safely, confirming the asset is installed correctly, works as specified, is safe to operate, and is fully documented before it is handed to operations. It runs across four stages: delivery and installation verification, where the plant is checked against the order and set in place; pre-commissioning, where services, fasteners, alignment and safety devices are checked before first energisation; commissioning, where the plant is run and its functions and safety systems are tested under controlled conditions; and handover, where the records, manuals and training are completed and operations formally accept the asset.

Commissioning is the gate between a machine being on site and a machine being safe to run in production, and skipping it is how latent faults, missing guards and undocumented assets reach the workforce. A staged checklist makes sure the plant is verified in the right order, so a fault is found on a controlled commissioning run rather than during the first real shift. It also creates the first entry in the asset record: the commissioning data, settings, manuals and certifications captured here become the baseline the machine history is built on, and the sign-off is the evidence that the plant commissioning duties in the Work Health and Safety Regulation and the safe-operation checks in AS 4024 were met before handover.

Learn more about maintenance and work orders in MapTrack.

Benefits of using this plant commissioning checklist

  • Safe start of life: function and safety tests under controlled conditions catch faults and missing guards before the plant runs in production.
  • Verified against order: delivery and install checks confirm the plant matches the specification and arrived complete, so shortfalls are raised before sign-off.
  • Right sequence: a staged checklist stops energisation before pre-commissioning checks are done, which is where many commissioning incidents start.
  • Complete asset record: commissioning settings, manuals and certifications captured at handover become the baseline for the machine history.
  • Clean handover: a defined acceptance step with documentation and training means operations take a plant they understand and can run safely.
  • Audit and warranty evidence: a dated commissioning record demonstrates WHS commissioning duties were met and supports later warranty and compliance questions.

Benefits of digitising forms in MapTrack

When you move your checklists from paper to MapTrack, you get:

  • Field users can easily scan a QR code to complete a form on mobile. Unlimited users.
  • Automatically get alerts when faults are identified.
  • Link every form digitally as a PDF to the relevant asset, location or person.
  • Receive a digital PDF copy with every submission to your email.
  • Ability to share forms digitally.
  • Build conditional logic (show or hide questions based on answers).
  • Take pictures or attach photos. Not possible with a paper-based form.
  • Electronic signatures.
  • Edit forms later without reprinting.
  • Restrict permissions (who can view, complete or approve).
  • Build forms with AI (describe what you need and MapTrack suggests the form).
  • Trigger work orders automatically when a fault is logged during an inspection.
  • Track service intervals by hours, kilometres or calendar date in one place.
  • Attach supplier invoices and parts receipts to each maintenance record.

Book a demo to see how MapTrack handles checklists.

Try MapTrack free for 30 days

Full access to every feature. No credit card required. Per-asset pricing so you scale as your fleet grows.

  • No credit card required
  • 30 days free trial
  • Cancel anytime

1-2 days/week saved

Bloody amazing! We used to spend 1-2 days a week tracking and managing our generators alone.
Saunders International

Steve McAllister

Asset Coordinator, Saunders International

What to include in a plant commissioning checklist

This plant commissioning checklist covers 10 key areas:

  • Plant identity: asset name, make, model, serial number and order reference
  • Delivery verification: plant received complete, undamaged and matching the specification
  • Installation: location, foundations or mounting, levelling, alignment and services connected
  • Pre-commissioning: fasteners, guards, lubrication, fluid levels and isolation points checked
  • Electrical and services: supply, earthing, controls and emergency stops verified before run
  • Function tests: each operating mode and control run and confirmed against specification
  • Safety system tests: guards, interlocks, emergency stops and protective devices proven
  • Performance: capacity, speed, pressure or output checked against the rated figures
  • Documentation: manuals, drawings, certifications, spares list and warranty recorded
  • Training and handover: operator and maintainer training done and operations acceptance signed

How to use this plant commissioning checklist

  1. Verify delivery and installation against the order: On arrival, check the plant is complete, undamaged and matches the purchase specification, then confirm it is installed in the right location, levelled, aligned and connected to its services. Raise any shortfall or damage before going further so it is resolved while the supplier is still accountable.
  2. Complete pre-commissioning checks before energising: Before the first run, work through the pre-commissioning checks: fasteners tight, guards fitted, lubrication and fluid levels correct, isolation points identified, and electrical supply, earthing and emergency stops verified. These checks confirm the plant is safe to energise rather than discovering a fault under power.
  3. Run function and safety tests under control: Energise the plant and test each operating mode and control against the specification, then prove every safety system: guards, interlocks, emergency stops and protective devices. Run these tests under controlled conditions with the right people present so any fault appears here, not on the first production shift.
  4. Confirm performance and capture documentation: Check capacity, speed, pressure or output against the rated figures and record the commissioning settings. Collect the manuals, drawings, certifications, spares list and warranty details so the asset record starts complete and the data is not chased down months later.
  5. Train operators and hand over to operations: Complete operator and maintainer training, walk through safe operation and isolation, then have operations formally accept the plant by signing the handover. The signed checklist confirms the asset is safe, documented and ready, and becomes the first entry in its maintenance history.

In MapTrack, you can schedule and track maintenance digitally. Each submission is stored as a timestamped PDF against the asset record.

Get the free templateEnter your email above to download the full plant commissioning checklist as a PDF.Back to download form

How often should you complete this checklist?

Use the commissioning checklist once per asset, when new fixed or mobile plant is brought into service, and again after any major overhaul, relocation or modification that changes how the plant is installed or operates. It is an event-driven control tied to the asset entering or re-entering service, not a recurring schedule, but the same staged method applies every time so nothing is skipped under time pressure.

The checklist also marks the start of the ongoing maintenance cycle. Once the plant is accepted, the commissioning data and settings become the baseline, the asset is added to the register and history card, and its preventive maintenance schedule begins from the in-service date. Treating commissioning as the first event in the asset lifecycle keeps the record continuous from day one rather than starting it at the first breakdown.

Frequently asked questions

The Work Health and Safety Regulation places duties on those who commission plant to make sure it is without risk to health and safety when used for its intended purpose, and it requires safety features and controls to be working. AS 4024 covers safe operation and guarding of machinery. A staged commissioning checklist that verifies installation, proves guards, interlocks and emergency stops, and records the result before handover provides evidence that these commissioning duties were met and that the plant was confirmed safe before anyone relied on it in production.

This is the plant-specific commissioning document. The general equipment-commissioning-checklist often covers just the final function test before use, whereas plant commissioning is broader because plant is installed: it runs across delivery and installation verification (foundations, mounting, levelling, alignment and services connected), staged pre-commissioning before first energisation, controlled commissioning runs, and a formal handover to operations. The extra stages exist because fixed and heavy mobile plant has foundations, services, alignment and guarding that all have to be verified in order. Use this plant checklist when the asset is installed and needs install, foundation, alignment and service checks; use the general equipment commissioning checklist for portable or bench equipment that mainly needs a final function test.

Pre-commissioning is the set of static, de-energised checks done before the plant runs for the first time: fasteners, guards, lubrication, fluid levels, alignment, isolation points, and electrical supply and earthing. Commissioning is the dynamic stage where the plant is energised and run, and its functions, performance and safety systems are tested under controlled conditions. The order matters: pre-commissioning confirms it is safe to energise, and commissioning then proves it works and is safe to operate. Doing them in sequence is how faults are caught safely.

Run the full checklist whenever an asset enters or re-enters service: new plant on first install, and again after a major overhaul, relocation to a new site or foundation, or a modification that changes how the plant is installed or operates. A minor repair under a normal work order does not need full commissioning, but any change that affects installation, guarding or capacity should be recommissioned so the plant is verified safe in its new configuration and the asset record is updated.

Yes, it is completely free. Open it in your browser, then use Print and choose Save as PDF to keep a copy or print it for the commissioning team. You do not need a MapTrack account. If you want to move beyond paper, MapTrack records commissioning against each new asset, stores the manuals and certifications, and starts the maintenance history and schedule from the in-service date. Start free or book a demo to see how.

Applicable regulatory standards

This template aligns with the following regulations and standards:

  • Work Health and Safety Regulation 2017, control of risks arising from the installation, construction or commissioning of plant (reg 201, reg 204)
  • ISO 55001:2024 Asset management (asset creation, commissioning and information handover)
  • AS 4024.1 Safety of machinery (guarding and safe operation verification)
  • ISO 45001:2018 Occupational health and safety management systems

Embed this free template on your website

Run an industry blog, trade association site, or training resource? Drop a preview of this free plant commissioning checklist straight into your page. The snippet is self-contained, needs no scripts, and links readers back to the full free template.

<div style="max-width:480px;font-family:system-ui,-apple-system,'Segoe UI',Roboto,sans-serif;border:1px solid #E5E7EB;border-radius:12px;padding:20px;background:#ffffff;">
  <p style="font-size:12px;font-weight:700;letter-spacing:0.05em;text-transform:uppercase;color:#0E7490;margin:0;">Free template</p>
  <p style="font-size:18px;font-weight:700;color:#071D49;margin:6px 0 0;">Plant commissioning checklist</p>
  <ul style="margin:12px 0 0;padding-left:18px;color:#374151;font-size:14px;line-height:1.6;">
    <li style="margin:4px 0;">Plant identity: asset name, make, model, serial number and order reference</li>
    <li style="margin:4px 0;">Delivery verification: plant received complete, undamaged and matching the specification</li>
    <li style="margin:4px 0;">Installation: location, foundations or mounting, levelling, alignment and services connected</li>
    <li style="margin:4px 0;">Pre-commissioning: fasteners, guards, lubrication, fluid levels and isolation points checked</li>
    <li style="margin:4px 0;">Electrical and services: supply, earthing, controls and emergency stops verified before run</li>
    <li style="margin:4px 0;">Function tests: each operating mode and control run and confirmed against specification</li>
  </ul>
  <p style="font-size:13px;color:#6B7280;margin:14px 0 0;padding-top:12px;border-top:1px solid #E5E7EB;">Free <a href="https://www.maptrack.com/templates/plant-commissioning-checklist" style="color:#071D49;font-weight:600;text-decoration:none;">Plant commissioning checklist</a> by MapTrack</p>
</div>

Please keep the “by MapTrack” attribution link in the snippet.

Need to schedule and track maintenance digitally?

Register every asset in MapTrack, attach digital forms, and get a complete history of every inspection, service and compliance record.

Maintenance and work orders · All templates · Pricing · Book a demo