Main Roads Traffic Management Video Requirements

Lachlan McRitchie

Lachlan McRitchie

Co-Founder & GM of Operations

Published 25 November 2026

Main Roads WA traffic management video under Specification 202, clause 202.65: when to record, 720p at 3 frames per second, 7-day keeping, Daily Diary.

Since 1 January 2025, any organisation running temporary traffic management on a Main Roads Western Australia worksite must video a drive-through of the traffic guidance scheme. Specification 202, clause 202.65, sets the detail: both directions, the full road width in public use, at least 720p and 3 frames per second, time and date stamped, kept at least 7 days.

Record at the start and end of each site working day, after every new or changed traffic guidance scheme (TGS), at least every four hours, and straight after a Relevant Incident. Log each recording’s time in the Daily Diary, and get footage to the Superintendent within 24 hours of a request from the Superintendent or the Principal.

Who Has to Record, and Since When

Section 5.2 of the Traffic Management for Works on Roads Code of Practice covers any organisation implementing temporary traffic management on a Main Roads worksite: works conducted by or on behalf of Main Roads. Main Roads’ frequently asked questions (FAQ) of March 2025 date it from 1 January 2025, and say it covers existing contracts and traffic management on paths.

Specification 202 Traffic Management puts the detail into Main Roads contracts at clause 202.65. It binds the Contractor, whose Traffic Management Plan (TMP) must set out detailed video recording procedures (clause 202.65(1)). Working for that contractor? Ask for those procedures before the job starts.

The rule came from the independent Regional Roadworks Signage Review of 2021 (FAQ question 1). It’s one of the four Main Roads video rules compared side by side in Main Roads WA video recording requirements. Pilot vehicles have their own, set out in WA pilot and escort vehicle requirements.

Worksites It Doesn’t Apply To

Section 5.2 of the Code of Practice excludes:

  • Short Term Low Impact Worksites, as set out in Part 5 of the Austroads Guide to Temporary Traffic Management (AGTTM);
  • Mobile Works, as set out in AGTTM Part 4;
  • events, as defined in the Traffic Management for Events Code of Practice;
  • responding to emergencies, or incident management.

The FAQ adds that day-to-day routine maintenance may not need video, while static worksites under AGTTM Part 3 do, and that events are excluded even on Main Roads roads. Clause 202.65 lists no exclusions: it applies on every site working day the TMP is in place (clause 202.65(2)). If your contract includes Specification 202 and the work is short term or mobile, confirm with the Superintendent.

Running Main Roads traffic management? See how inspection forms and footage requests work in MapTrack.

Book a demo

30 minutes on Microsoft Teams

The Rule as a Checklist

  • Before the job: get the TMP’s video procedures, check the dash cam records at least 720p and 3 frames per second with a time and date stamp, and carry a backup SD card (clauses 202.65(1) and (5), FAQ question 9).
  • Every recording: both directions, the full road width in public use, every traffic control device, and any detours, sidetracks or temporary driving surfaces (clauses 202.65(1), (3) and (5)(b)).
  • When: at each point in the table below, never more than four hours apart.
  • Daily Diary: each recording’s time, and any changes or improvements it led to (clause 202.65(4)).
  • Afterwards: keep every recording at least 7 days, keep anything someone authorised has asked for, and get footage to the Superintendent within 24 hours when the Superintendent or the Principal asks (clauses 202.65(5)(a) and (6)(b)).
  • Missed one: a Non-conformance Report under Specification 201 (clause 202.65(8)).

When to Record

Clause 202.65 asks for video in both directions on every site working day the TMP is in place, at each of these points.

WhenClauseDetail
Start of each site working day202.65(3)(a)Before anyone changes a traffic control device or driving surface.
After a new or changed TGS202.65(3)(b)Immediately after it’s implemented.
During the day202.65(3)(c)No more than four hours apart during site working hours.
End of each site working day202.65(3)(d)And again once any relevant after care TGS is in place.
After a Relevant Incident202.65(3)(e)Immediately, then to the Superintendent straight away (clause 202.65(6)(a)).

A Relevant Incident is any Traffic Incident, or a Safety Incident that implementing or altering the TMP caused, or could reasonably have prevented or reduced (clause 202.03). A Traffic Incident impedes the normal flow of traffic beyond what the TMP requires, or is a crash the works may have caused that affects public road users, including cyclists and pedestrians.

What the Video Must Show

Clause 202.65 sets what each recording covers and its minimum quality, but names no camera model: the Code of Practice asks for a dash cam or similar.

WhatMinimumWhere it’s set
DirectionsBoth directions of travelClause 202.65(3)
Road widthThe full width of road public road users are using, with its traffic control devices, clearly shownClause 202.65(5)(b)
Devices and surfacesEvery traffic control device for the work, and the condition of any detours, sidetracks or temporary driving surfacesClause 202.65(1)
Resolution720pClause 202.65(5)(c)
Frame rate3 frames per secondClause 202.65(5)(d) and Code of Practice section 5.2
Time and dateStamped on every recordingClause 202.65(5)(e)

The FAQ says the video records the signs and devices at each inspection, correct and upright, not the incident itself. Recording must stay within the Road Traffic Code 2000 (WA) and other relevant laws (clause 202.65(7)). The FAQ suggests a dash cam switched on only for the drive-throughs, plus a backup SD card: that way, a 128 GB card should generally hold 7 days of footage.

How Long to Keep the Footage

Seven days is a minimum, not a target. After 7 days from the date of recording, clause 202.65(5)(a) lets you delete or overwrite video only if nobody authorised has asked for it.

RecordKeep itSource
Drive-through videoAt least 7 days from the date of recordingClause 202.65(5)(a) and Code of Practice section 5.2
Video someone authorised has asked forDon’t delete or overwrite it. If Main Roads asked, the FAQ says it’s kept under Main Roads’ normal record keeping proceduresClause 202.65(5)(a) and FAQ question 10
TMP and Daily DiaryMain Roads recommends storing them securely for at least 7 years from completion of the worksCode of Practice section 5.2

The FAQ leaves it to the traffic management company or contractor to keep video longer than 7 days if it wants to.

Who Can Ask for the Footage

Clause 202.65(6) sets two deadlines for getting video to the Superintendent:

  • On request: within 24 hours of a request from the Superintendent or the Principal.
  • After a Relevant Incident: immediately, without waiting to be asked.

Others can ask too. Clause 202.65(5)(a) names the police and WorkSafe among those authorised under legislation whose request stops deletion after 7 days, and the 2025 FAQ says requested footage goes to the relevant Main Roads officer, WA Police or WorkSafe.

How It Ties Into the Site Inspection and Daily Diary

  • The inspection: Specification 202 asks for all traffic management signs and devices to be inspected at least every two hours while the TMP is in place and workers are on site, using Main Roads’ Operational Check and Onsite Inspection Checklist (clauses 202.61(2) and (3)). The FAQ says to film at the same time, which also keeps you inside the four-hour limit.
  • The diary: clause 202.65(4) asks for each recording’s time, and any changes or improvements needed or made after it. The Code of Practice says the Daily Diary must at least be based on Main Roads’ Traffic Management Daily Diary Template, which has a row for “Drive Through Video Recording conducted as per Main Roads Requirements”.
  • Handing it in: Specification 202 asks for completed daily diaries within 24 hours after the shift (clause 202.61(6)), and a copy of each within 7 days of completion (clause 202.63(5)). Within 24 hours meets both.

Main Roads wants feedback on a draft update of the Daily Diary template by 11 January 2027, on its Working on roads page. The draft keeps the video row.

A Sample Daily Recording Log

Clause 202.65 sets no log format. This layout keeps a day’s recordings in one place; still copy each time into the Daily Diary (clause 202.65(4)). Head it with the site, date, TMP and TGS numbers, camera, and earliest overwrite date: 7 days after recording, if nobody has asked for the footage.

Recording pointClause 202.65TimeBoth directionsFile or clip nameChanges or improvements after itRecorded by
Start of day, before any changes(3)(a)
New or changed TGS (number and revision)(3)(b)
Within four hours of the last(3)(c)
Within four hours of the last(3)(c)
End of day(3)(d)
After care TGS in place(3)(d)
Relevant Incident (time sent to the Superintendent)(3)(e) and (6)(a)

At the foot, note any request: who asked, when, and when the footage reached the Superintendent.

If a Recording Is Missing

Safety comes first: clause 202.65(8) says nothing in the clause stops the Contractor taking urgent action to keep workers and road users safe. But if any part of the clause isn’t met, for any reason, a Non-conformance Report under Specification 201 Quality Management must be produced. The Superintendent can also audit compliance at any time during the contract (clause 202.64(2)), and the FAQ notes the video may be requested after a safety incident.

Where Clause 202.65 and the 2025 FAQ Differ

The FAQ and the Code of Practice give the rule in outline. Clause 202.65 has the detail, and the FAQ points to it. Where your contract includes Specification 202, follow the clause.

Topic2025 FAQ and Code of Practice section 5.2Specification 202, clause 202.65
When to recordAt the same time as the existing site inspectionsStart and end of each site working day, after each new or changed TGS, no more than four hours apart, and after any Relevant Incident
What to recordThe implemented traffic guidance schemeBoth directions, the full road width in public use, every traffic control device, and any detours, sidetracks or temporary driving surfaces
QualityAt least 3 frames per second (Code of Practice)At least 720p and 3 frames per second, time and date stamped
Who can stop deletion after 7 daysMain Roads, by asking for the footageThe Superintendent, the Principal, or anyone authorised under relevant legislation, including the police and WorkSafe
Handing it overAs soon as possible, or as the Main Roads contract requiresTo the Superintendent within 24 hours of a request from the Superintendent or the Principal, and immediately after a Relevant Incident
Daily DiaryRecord the video in the daily diaryRecord each recording’s time, and any changes or improvements following it
ExclusionsShort Term Low Impact Worksites, Mobile Works, events, emergencies and incident managementNone listed in the clause
A missed recordingNot coveredA Non-conformance Report under Specification 201 Quality Management

Not sure which applies to a job? Ask the Superintendent, or Main Roads at roadsafety@mainroads.wa.gov.au, the address the FAQ gives.

What MapTrack Does and Doesn’t Do

MapTrack is an asset management platform that also supplies AI dash cams. It’s the platform behind 600,000+ assets tracked since 2012.

Running AI dash cams in MapTrack? Account owners can request footage from a trip, with faces and number plates blurred. Blur is an option on each request. See video telematics.

For the paperwork, build the site inspection and Daily Diary as custom forms that crews fill in on a phone and sign on the screen. Base them on Main Roads’ checklist and diary template; clause 202.61(2) names Main Roads’ own checklist, so check a form version with the Superintendent first. Forms already on the phone can be submitted without signal. The photos and signature are saved with each submission and printed on its PDF. A failed inspection check automatically raises a corrective work order.

Where it doesn’t fit:

  • It isn’t a Main Roads approval. Main Roads sets these rules, and nothing on this page is endorsed by Main Roads.
  • Keep the camera’s original recordings for at least 7 days, and longer once anyone authorised asks for them.
  • Don’t use a requested clip as your drive-through record unless you’ve checked it shows both directions and the full road width, at 720p and 3 frames per second or better, time and date stamped.
  • Don’t rely on a time-lapse as the record.
  • The drive-throughs, the diary entries and the 24-hour hand-over stay with your crew and company.

Forwarding this to whoever signs off on the contract? The clauses and Sources are Main Roads’ own documents, and a demo is 30 minutes on Microsoft Teams.

Sources

Every rule here comes from these Main Roads WA documents, fetched from mainroads.wa.gov.au and checked on 25 November 2026.

This guide summarises Main Roads’ documents as of November 2026. Your contract and Main Roads’ current documents govern.

Running Main Roads worksites? See it with your own crews

Site inspections and daily diaries as signed forms with PDFs, a failed check raising a work order, and footage requests from a trip in MapTrack.

  • No credit card required

About the author

Lachlan McRitchie

Lachlan McRitchie

Co-Founder & GM of Operations

Lachlan leads operations at MapTrack, bringing 10+ years of enterprise technology experience across mining, construction and heavy industry. Before MapTrack, he held senior roles at Workato (integration and automation) and AppDynamics/Cisco (application performance), working directly with ASX-listed organisations to modernise their technology stacks. His deep understanding of field operations and blue-collar workflows shapes how MapTrack solves real problems for asset-intensive teams.

View LinkedIn profile →

FAQ

Who has to record drive-through video on a Main Roads worksite?

Any organisation running temporary traffic management on a Main Roads worksite, meaning works by or on behalf of Main Roads, under section 5.2 of the Traffic Management for Works on Roads Code of Practice. Main Roads’ March 2025 FAQ says it has applied since 1 January 2025, existing contracts and paths included. Clause 202.65 of Specification 202 Traffic Management sets the detail in Main Roads contracts.

How often do we have to record the drive-through video?

In both directions at the start of each site working day, straight after any new or changed traffic guidance scheme (TGS), at least every four hours during site working hours, at the end of the day and after any after care TGS, and immediately after a Relevant Incident. That’s clause 202.65(3) of Specification 202 Traffic Management. The 2025 FAQ simply says to film with each site inspection.

What resolution and frame rate does traffic management video need?

At least 720p and 3 frames per second, with a time and date stamp, under clause 202.65(5) of Main Roads’ Specification 202 Traffic Management. Each recording must clearly show the full width of road public road users are using, with its traffic control devices. The Code of Practice asks for a dash cam or similar, recording at least 3 frames per second.

How long do we have to keep traffic management dash cam footage?

At least 7 days from the date of recording, under clause 202.65(5)(a) of Specification 202 Traffic Management. After that you can delete or overwrite it only if nobody authorised has asked for it: the Superintendent, the Principal, or anyone authorised by law, including the police and WorkSafe. Seven days is a minimum, and Main Roads’ 2025 FAQ leaves keeping it longer up to you.

Who can ask for the footage, and how fast do we hand it over?

The Superintendent or the Principal can ask, and the video must reach the Superintendent within 24 hours of the request, under clause 202.65(6) of Specification 202 Traffic Management. After a Relevant Incident it goes to the Superintendent immediately, unasked. The police and WorkSafe can also ask, and Main Roads’ 2025 FAQ says requested footage goes to the relevant Main Roads officer, WA Police or WorkSafe.

Which worksites don’t need traffic management video?

Short Term Low Impact Worksites (Austroads Guide to Temporary Traffic Management Part 5), Mobile Works (Part 4), events, and responding to emergencies or incident management, under section 5.2 of Main Roads’ Traffic Management for Works on Roads Code of Practice. The 2025 FAQ says routine maintenance may not need it, but static worksites do. Clause 202.65 of Specification 202 lists no exclusions, so check your contract.

What goes in the Daily Diary about the video?

The time of each recording, plus any changes or improvements needed or made after it, under clause 202.65(4) of Specification 202 Traffic Management. The Code of Practice says the Daily Diary must at least be based on Main Roads’ Traffic Management Daily Diary Template, which has a row for “Drive Through Video Recording conducted as per Main Roads Requirements”. Completed diaries go to the Superintendent within 24 hours after the shift (clause 202.61(6)).

What happens if we miss a drive-through recording?

A Non-conformance Report under Specification 201 Quality Management must be produced for any non-compliance with clause 202.65 of Specification 202 Traffic Management, for any reason. Nothing in the clause stops urgent action to keep people and road users safe. The Superintendent can audit compliance at any time during the contract, and Main Roads’ 2025 FAQ says the video may be requested after a safety incident.