To save as PDF: use your browser's Print → Save as PDF or Print to PDF. This permit prints as 2 pages (A4).
Authorise work at height after verifying all safety controls are in place
PAGE 1 OF 2
Pre-Work Checklist
Mark the applicable column for each item: P = Pass | F = Fail | N/A = Not applicable. Do not issue permit if any critical item fails.
| # | Check | P | F | N/A | Notes / Action |
|---|---|---|---|---|---|
| Documentation & Planning | |||||
| 1 | Risk assessment completed for the task | ||||
| 2 | SWMS reviewed and signed by all workers | ||||
| Fall Prevention & Protection | |||||
| 3 | Edge protection in place (guardrails, mid-rails, toe boards) | ||||
| 4 | Penetrations covered or barricaded | ||||
| 5 | Anchor points rated and inspected (min 15 kN or per standard) | ||||
| 6 | Fall arrest system inspected: harness, lanyard, SRL | ||||
| Rescue & Emergency | |||||
| 7 | Rescue plan in place and communicated | ||||
| 8 | Rescue equipment available (e.g. descent device, first aid) | ||||
| 9 | Workers briefed on rescue procedure | ||||
| 10 | Emergency contacts displayed on-site | ||||
| # | Check | P | F | N/A | Notes / Action |
|---|---|---|---|---|---|
| Site Controls | |||||
| 11 | Exclusion zone established and barricaded below work area | ||||
| 12 | Signage in place (Working at Heights: Authorised Personnel Only) | ||||
| 13 | Wind conditions acceptable (<40 km/h or per site rules) | ||||
| 14 | Lighting adequate for the task | ||||