To save as PDF: use your browser's PrintSave as PDF or Print to PDF. This checklist prints as 2 pages (A4).

UPS Battery Inspection Checklist

Quarterly inspection and testing record for UPS battery systems.

Company logo

PAGE 1 OF 2

UPS & Battery Details

Inspection Items

Circle or mark the applicable column for each item: P = Pass  |  F = Fail  |  N/A = Not applicable. Record notes for any F.

# Check P F N/A Notes / Action
Environment & Safety
1Battery room or cabinet ventilation: adequate airflow, no obstructions
2Room temperature recorded: within 20-25°C recommended range
3Hydrogen detection system (VLA batteries): functional
4Spill containment: in place, no evidence of electrolyte leaks
5Emergency eyewash and shower station: accessible, functional
6PPE available: acid-resistant gloves, face shield, apron
Visual Inspection
7Battery jars / cases: no cracks, bulging, leaking or discolouration
8Terminal posts: no corrosion, oxidation or white deposits
9Inter-cell connections: tight, no discolouration or heating marks
10Cable connections to UPS and DC bus: tight, properly torqued
11Battery rack or cabinet: structurally sound, no corrosion
12Battery labels and polarity markings: legible
Electrical Measurements
13Float voltage (entire string): recorded, within manufacturer tolerance
14Individual cell / unit voltages: recorded, compared to baseline
15Cells deviating more than 0.05V from average: flagged for investigation
16Pilot cell specific gravity (VLA): recorded, compared to baseline
17Inter-cell connection resistance: measured, compared to baseline
18Overall string resistance: measured and recorded
Charger & UPS Status
19UPS operating mode: online / double conversion confirmed
20Charger output voltage: within specification
21Charger output current: steady, not cycling
22UPS alarm panel: no active alarms or faults
23UPS load level: recorded (kVA or percentage)
24Transfer switch: tested to battery and back to mains
UPS Battery Inspection - Page 2 of 2
UPS ID
Date
Inspector
# Check P F N/A Notes / Action
Capacity & Performance
25Time since last capacity test: recorded (annual test required per IEEE)
26Last capacity test result: percentage of rated capacity noted
27Batteries below 80% rated capacity: flagged for replacement per IEEE 1188
28Battery age vs expected life: assessed, replacement planning if nearing end of life
29Thermal scan (if performed): no hot spots on connections or cells
Documentation & Close-out
30Previous inspection report: reviewed, open items addressed
31Measurement data: recorded in battery log or CMMS
32Battery monitoring system (if fitted): data reviewed, alerts acknowledged
33Maintenance records: updated with date, readings and actions
34Next inspection scheduled: date recorded on system and inspection tag
Overall Result
PASS: all items satisfactory, batteries serviceable FAIL: defect(s) identified, see table below

Defects & Action Required  (list any item marked F: reference item # from checklist)

Item # Defect description Action taken / reported to Rectified by / date

Declaration

I declare that I have completed this quarterly battery inspection in accordance with IEEE 450 / IEEE 1188 recommended practices and site procedures. All measurements have been recorded accurately. Any cells or conditions outside acceptable limits have been reported and escalated for corrective action.

Inspector / Technician Sign-off
Signature
Print name
Date & time
Facilities Manager / Electrical Supervisor Acknowledgement
Signature
Print name
Date