System & Inspection Details

Inspection Items

Circle or mark the applicable column for each item: P = Pass  |  F = Fail  |  N/A = Not applicable. Record notes for any F.

# Check P F N/A Notes / Action
Control Valves & Water Supply
1Main control valve: open, locked, sealed and tagged
2Sectional / zone control valves: correct position, sealed
3Water supply pressure: static reading recorded (kPa / psi)
4Water supply pressure: residual reading recorded via main drain
5Main drain test: flow and pressure compared to previous results
6Fire pump (if fitted): auto-start tested on pressure drop
Alarm Devices & Monitoring
7Water flow alarm switch: activated via test, alarm received at panel
8Alarm signal received at monitoring centre: confirmed
9Pressure switches: tested, alarm at correct set point
10Water motor gong (if fitted): activated during flow test
11Supervisory signals: tamper switches tested on all monitored valves
Sprinkler Heads & Piping
12Sprinkler heads (sample): no damage, corrosion, paint or loading
13Sprinkler head clearance: minimum 300mm below storage maintained
14Spare sprinkler heads: cabinet stocked per AS 1851 / NFPA 25 requirements
15Pipe hangers and supports: secure, no sagging or missing hangers
16Visible piping: no leaks, corrosion, mechanical damage or obstructions
Fire Department Connection (FDC)
17FDC: visible, accessible, caps in place
18FDC check valve: not leaking, couplings undamaged
19FDC signage: present and legible
20Clear access to FDC: no obstructions within required clearance
Gauges & Drain Valves
21System pressure gauges: readable, in calibration date
22Air gauge (dry systems): pressure within acceptable range
23Auxiliary drain valves (dry systems): drained this quarter
24Inspector test valve: opened, flow confirmed, alarm activated
Sprinkler System Quarterly Inspection - Page 2 of 2
Building
Date
Inspector
# Check P F N/A Notes / Action
Booster Pump & Tank (if applicable)
25Pump starts on pressure drop: confirmed
26Pump running pressure and flow: within design parameters
27Pump controller: no fault alarms, auto mode enabled
28Diesel engine pump (if fitted): fuel level, battery, coolant checked
29Water storage tank level: at or above minimum required level
30Tank level switches and alarms: functional
Records & Compliance
31Previous quarterly report: reviewed, open items closed
32AS 1851 / NFPA 25 logbook: entries current
33Impairment procedures: system impairments properly managed and notified
34Fire brigade / monitoring company: notified before and after testing
35Inspection tag or label: updated with date and inspector details
Overall Result
PASS: all items satisfactory, system operational FAIL: defect(s) identified, see table below

Defects & Action Required  (list any item marked F: reference item # from checklist)

Item # Defect description Action taken / reported to Rectified by / date

Declaration

I declare that I have completed this quarterly inspection and functional testing in accordance with AS 1851 Section 2 and NFPA 25 requirements. All tests and inspections are recorded accurately. Any impairments or deficiencies have been reported to the building owner or responsible person and the fire monitoring company.

Inspector / Technician Sign-off
Signature
Print name
Date & time
Building Manager / Fire Safety Officer Acknowledgement
Signature
Print name