General construction site safety walkthrough per OSHA 29 CFR 1926
PAGE 1 OF 2
| # | Inspection Item | P/F | Notes |
|---|---|---|---|
| Fall Protection | |||
| 1 | Fall protection provided at 1.8 m (6 ft) or above | ||
| 2 | Guardrails in place at all open edges and holes | ||
| 3 | Personal fall arrest systems inspected and worn | ||
| 4 | Floor openings and holes covered and marked | ||
| 5 | Safety nets installed where required | ||
| 6 | Workers trained on fall hazards and controls | ||
| Scaffolding | |||
| 7 | Scaffolds erected on stable foundation | ||
| 8 | Guardrails and toeboards installed on all platforms | ||
| 9 | Competent person has inspected scaffold | ||
| 10 | Safe access provided (ladder, stair) | ||
| 11 | Scaffold not overloaded beyond rated capacity | ||
| Electrical Safety | |||
| 12 | GFCI protection on all temporary circuits | ||
| 13 | Temporary wiring installed per code | ||
| 14 | Extension cords in good condition, no splices | ||
| 15 | Overhead power line clearances maintained | ||
| 16 | Electrical panels accessible and labelled | ||
| Excavation and Trenching | |||
| 17 | Excavations over 1.5 m (5 ft) have protective system | ||
| 18 | Competent person inspected excavation daily | ||
| 19 | Spoil set back at least 600 mm (2 ft) from edge | ||
| 20 | Safe means of egress within 7.5 m (25 ft) of workers | ||
| 21 | Underground utilities located and marked | ||
| PPE and Housekeeping | |||
| 22 | Hard hats worn in designated areas | ||
| 23 | High-visibility vests worn where required | ||
| 24 | Eye and hearing protection used for applicable tasks | ||
| 25 | Work areas clear of debris and trip hazards | ||
| 26 | Walkways and access routes unobstructed | ||
| 27 | Waste and materials stored in designated areas | ||
| Fire Prevention and Emergency | |||
| 28 | Fire extinguishers present and accessible | ||
| 29 | Hot work permits issued where required | ||
| 30 | Flammable materials stored properly | ||
| 31 | Emergency evacuation routes posted and clear | ||
| 32 | First aid kit stocked and accessible | ||
| Signage and Permits | |||
| 33 | Site safety signage displayed at entry points | ||
| 34 | Danger and warning signs posted at hazard areas | ||
| 35 | Barricades and fencing around hazardous zones | ||
| 36 | All required permits current and posted (hot work, confined space) | ||
| 37 | Site induction records current for all workers on site | ||
I confirm that all items have been inspected/completed as indicated above. Any defects or concerns have been noted and reported.