Preliminary crane lift feasibility assessment - AS 2550:2021
PAGE 1 OF 2
Crane Option Comparison
Assess at least two crane options. Record capacity at the required radius and percentage of rated capacity the lift will use.
| Parameter | Option A | Option B |
|---|---|---|
| Crane type / model | ||
| Boom length (m) | ||
| Capacity at radius (t) | ||
| % of rated capacity | ||
| Tail swing (m) | ||
| Transport dimensions | ||
| Set-up area required | ||
| Estimated hire cost |
Site Constraints and Hazard Register
Record each constraint or hazard identified during the site review. Assign an initial risk rating and note proposed controls.
| # | Constraint / Hazard | Details | Risk | Proposed Control |
|---|---|---|---|---|
| Access and Ground | ||||
| 1 | Access route for crane delivery | |||
| 2 | Ground bearing capacity at set-up | |||
| 3 | Underground services in set-up area | |||
| Overhead and Adjacent | ||||
| 4 | Overhead power lines | |||
| 5 | Adjacent structures in swing arc | |||
| 6 | Other cranes operating nearby | |||
| Public and Environmental | ||||
| 7 | Public access / pedestrian areas | |||
| 8 | Traffic management requirements | |||
| 9 | Wind / weather exposure | |||
| 10 | Other (specify) | |||
Risk: L = Low, M = Moderate, H = High, E = Extreme.
Critical Lift Determination (AS 2550 Section 8)
Tick any criteria that apply. If any box is ticked, a critical lift plan will be required.
| Tick | AS 2550 Section 8 Criterion |
|---|---|
| Load will exceed 80% of crane rated capacity at planned radius | |
| Tandem lift (two or more cranes required) | |
| Load path over occupied buildings or public areas | |
| Lift within minimum approach distance of live power lines | |
| Load has no certified lifting points | |
| Personnel on the load or hook block |
Declaration
I declare that this lift study has been prepared in accordance with AS 2550:2021 (Cranes, hoists and winches - safe use). The load weight, dimensions and lift geometry have been obtained from the best available sources and are recorded with their source reference. Site constraints and hazards have been identified through a site review and are documented above. Crane options have been assessed against the required lift parameters. Where any AS 2550 Section 8 critical lift criteria are triggered, this has been flagged so that a critical lift plan can be initiated. This lift study is a preliminary assessment; a full lifting plan or critical lift plan must be prepared before the lift takes place.