To save as PDF: use your browser's Print then Save as PDF or Print to PDF. This checklist prints as 2 pages (Letter).

Hydraulic Press Inspection Checklist

Pre-shift safety inspection per OSHA 29 CFR 1910.217 and ANSI B11.2.

Company logo

PAGE 1 OF 2

Press Identification

Pre-Shift Inspection Items

Mark OK, Fail or N/A for each item. Record details of any deficiency in the Notes column. Do not operate the press if any item is marked Fail.

# Inspection Item OK Fail N/A Notes / Deficiency Details
Hydraulic System
1Hydraulic fluid level within operating range (sight glass / dipstick)
2Fluid condition acceptable (no discoloration, burnt odor or visible contamination)
3Hoses free of bulging, cracking, abrasion or weeping
4Fittings and connections tight with no leaks
5Cylinder rods free of scoring, pitting or seal leakage
6Pressure gauge reads within normal range at idle
7Hydraulic pump running without abnormal noise or vibration
8Filter condition indicator in acceptable range
Mechanical Structure
9Frame free of visible cracks, distortion or damage
10Bolster plate clean, flat and undamaged
11Ram and slide travel smooth through full stroke (inch mode)
12Gib adjustment within tolerance, no excessive play
13Die clamps secure and correctly positioned
14Counterbalance functioning correctly
Hydraulic Press Inspection - Page 2 of 2
Asset ID
Date
Inspector
# Inspection Item OK Fail N/A Notes / Deficiency Details
Point-of-Operation Safeguarding
15Fixed guards in place, secure and undamaged
16Light curtain aligned and functioning (beam-break test passed)
17Two-hand controls operating correctly (anti-tie-down test passed)
18Presence-sensing device / pullback device functioning (if fitted)
19Interlock switches on all access doors and panels operational
Electrical & Controls
20Main disconnect functional, labeled and accessible
21All emergency stop buttons tested and functional (all stations)
22Cycle selector (single stroke / continuous / inch) operating correctly
23Anti-repeat function verified (press does not re-cycle without new actuation)
24Foot pedal or palm buttons operating correctly
Lubrication & Work Area
25Slide and gib lubrication adequate
26Auto-lube system reservoir level adequate (if equipped)
27Floor around press clean, dry and free of tripping hazards
28Adequate lighting at point of operation and controls
29LOTO procedure posted and LOTO devices available at press
30Scrap bin accessible, material staging area clear
Overall Result
All items OK - press released for production One or more items failed - press locked out, maintenance notified

Declaration

I declare that I have inspected the above hydraulic press and tested all point-of-operation safeguards, emergency stops and controls in accordance with the pre-shift inspection procedure. All findings have been accurately recorded on this checklist. Where any item has been marked as Fail, I have applied an out-of-service tag to the main control, notified maintenance and documented the deficiency above. The press has not been released for production until all failed items have been corrected and re-inspected.

Operator / Inspector Sign-off
Signature
Print name
Date
Supervisor Acknowledgment
Signature
Print name
Date