Generator Inspection Checklist

Pre-use & periodic inspection record: complete before each operation

Company logo

PAGE 1 OF 2

Generator & Inspector Details

Inspection Items

Circle or mark the applicable column for each item: P = Pass  |  F = Fail  |  N/A = Not applicable. Record notes for any F.

# Check P F N/A Notes / Action
External & Physical Condition
1Housing / enclosure: no cracks, damage, doors latch and seal correctly
2Ventilation openings: clear of debris, no blockages
3Frame & mounting: secure, no loose bolts, anti-vibration mounts intact
4Exhaust system: secure, no cracks, directed safely away from openings and personnel
5Fuel system: tank, lines and fittings secure, no visible leaks or damage
6Spill containment / bund: in place, no overflow, free of debris
7Labels & warning signs: legible, in place (voltage, hazard, earthing)
8General cleanliness: no excessive oil, grime or combustible material near unit
Fluids & Levels
9Engine oil level: dipstick within correct range, oil condition acceptable
10Coolant level: reservoir within correct range (check when cold)
11Fuel level: sufficient for required runtime; fuel type correct
12No visible fluid leaks: oil, coolant or fuel under or around generator
Engine & Mechanical
13Air filter: clean, unobstructed, housing secure
14Drive belts / fan belt: condition, correct tension, no fraying
15Cooling fan: unobstructed, guard in place and secure
16Battery: terminals clean and secure, no corrosion, charge indicator OK
17Hoses & connections: no cracks, perishing or loose clamps
18Engine start: starts promptly, no excessive smoke, runs smoothly at idle
19Unusual noises or vibrations: none detected during run
Generator Inspection Checklist - Page 2 of 2
Generator ID
Date
Inspector
# Check P F N/A Notes / Action
Electrical Output & Controls
20Output voltage: within rated spec (e.g. 240 V / 415 V), measured at panel
21Output frequency: within rated spec (50 Hz AU/NZ)
22Control panel: gauges and indicators functional, no fault/alarm warnings
23Circuit breakers / MCBs: not tripped, ratings correct, switches freely
24RCD / safety switch: present and tested functional (push test button)
25Earth / ground connection: secure, correct continuity, bonding intact
26Output cables & leads: no damage, insulation intact, no exposed conductors
27Outlet sockets: undamaged, covers in place, correct rating for connected loads
28Auto-start / transfer switch: tested and operational (if fitted)
29Emergency stop / shutdown: operational, reset correctly after test
30Hour meter: reading recorded, matches maintenance schedule
Safety Equipment
31Fire extinguisher: present, in date, accessible, pin secure
32PPE required: appropriate PPE available and used during inspection
33Exclusion zone: adequate clearance maintained around operating unit
Compliance & Documentation
34Test & tag current: electrical tag in date (if required by site/jurisdiction)
35Service record current: last service within required interval
36Operating manual on site: accessible for reference
37Permits / compliance documentation: in place if required (e.g. electrical safety)
Overall Result
PASS: all items satisfactory, generator fit for use FAIL: defect(s) identified, see table below

Defects & Action Required  (list any item marked F: reference item # from checklist)

Item # Defect description Action taken / reported to Rectified by / date

Declaration

I declare that I have completed this generator inspection before operating this unit. I have recorded all findings accurately and reported any defects or non-compliant items to my supervisor. The generator will not be operated until any faults that affect safety or compliance have been rectified. I understand that failure to complete an inspection or to report defects may breach company policy and WHS obligations.

Inspector Sign-off
Signature
Print name
Date & time
Supervisor / Reviewer Acknowledgement
Signature
Print name
Date