# Check P F N/A Notes / Action
Erosion & Sediment Control
1Sediment fences: installed, intact and not overtopped
2Sediment basins / traps: functional, not full, outlets clear
3Stabilised entry/exit points: rumble grids or wash-down bays operational
4Stockpile management: stockpiles covered or bunded where required
5Diversion drains: directing clean water around disturbed areas
Waste Management
6General waste: bins provided, not overflowing, lids closed
7Recycling: separated bins for cardboard, metal, concrete where required
8Hazardous waste: stored in labelled containers in bunded areas
9Waste tracking: waste removal records and dockets up to date
Chemical & Fuel Storage
10Fuel storage: tanks or drums in bunded area, bund capacity adequate
11Spill kits: available, stocked and accessible near storage areas
12SDS: Safety Data Sheets current and accessible for all chemicals on site
13Refuelling: drip trays in use, no visible spills or staining on ground
Environmental Site Inspection - Page 2 of 2
Site
Date
Inspector
# Check P F N/A Notes / Action
Dust & Air Quality
14Dust suppression: water carts or sprinklers operating as needed
15Exposed areas: disturbed ground stabilised or covered to reduce dust
16Vehicle speed: site speed limits observed to minimise dust generation
Noise & Vibration
17Work hours: noisy activities within approved hours per conditions of consent
18Noise mitigation: barriers, enclosures or mufflers in use where required
Water Quality & Discharge
19Stormwater drains: protected from sediment-laden runoff
20Dewatering: discharge water tested and within licence limits (if applicable)
21Wash-out areas: concrete wash-out contained, not draining to waterways
Flora, Fauna & Heritage
22Vegetation: exclusion zones intact, no unauthorised clearing
23Fauna: no evidence of trapped or injured wildlife, nesting sites protected
24Heritage items: identified areas fenced and undisturbed
Overall Result
PASS: all items satisfactory ACTION REQUIRED: item(s) to rectify, see below FAIL: stop work, report to project manager

Corrective Actions  (list any item marked F: reference item # from checklist)

Item # Issue description Action taken / reported to Rectified by / date

Declaration

I declare that I have completed this environmental site inspection. I have reported any non-compliant items to the project manager and/or environmental officer. Any items requiring corrective action have been documented above and will be addressed within the specified timeframe.

Inspector Sign-off
Signature
Print name
Date & time
Project Manager / Environmental Officer Acknowledgement
Signature
Print name
Date