AS 2550 Section 8 - Special lifting applications
PAGE 1 OF 3
Critical Lift Classification
Tick all criteria that apply to this lift. At least one must be ticked for this form to be used.
| Tick | Criterion |
|---|---|
| Load exceeds 80% of crane rated capacity at the planned radius | |
| Tandem lift (two or more cranes) | |
| Load travels over occupied buildings or public areas | |
| Lift within minimum approach distance of live overhead power lines | |
| Load has no certified lifting points (engineered or non-standard item) | |
| Personnel riding on the load or hook block | |
| Other (specify below) |
Site Hazards and Controls
Tick Y (yes), N (no) or N/A for each item. All items marked N must be resolved before the lift proceeds.
| # | Item | Y | N | N/A | Control / Notes |
|---|---|---|---|---|---|
| 1 | Ground bearing confirmed by engineer for crane and outriggers | ||||
| 2 | Outrigger pads / mats sized per engineering calculation | ||||
| 3 | Overhead power lines: safe approach distances confirmed | ||||
| 4 | Underground services located and marked | ||||
| 5 | Adjacent structures clear of boom swing and load path | ||||
| 6 | Exclusion zone barricaded, signed and marshalled | ||||
| 7 | Occupied areas below load path evacuated or shielded | ||||
| 8 | Wind speed confirmed within plan limit | ||||
| 9 | All rigging inspected and within WLL and inspection dates | ||||
| 10 | Communication tested between all key personnel |
Declaration
I declare that this critical lift plan has been prepared in accordance with AS 2550 Section 8 (Special lifting applications) and BS 7121 (Code of practice for safe use of cranes). The load weight has been verified from a reliable source. Engineering calculations for crane stability, ground bearing and rigging loads have been completed and reviewed by a qualified engineer. All rigging components are within their rated working load limits and current inspection dates. Site hazards have been assessed, exclusion zones established, and abort criteria defined. All personnel have been briefed on the full lift sequence, hold points, communication protocols, abort criteria and emergency procedures. This plan must be revised, re-calculated and re-approved if any conditions change.